South Melbourne House 4 - joinery installation

Brief:

To install new TV joinery and storage to living room.

Design Constraints:

To work within the existing constraints of a 3rd floor established living room.

Design Resolution:

The new joinery was on the third floor of this 3 storey town house so large elements had to be considered.

Design, Documentation: 15 weeks

Construction: 4-6 weeks